Project Profile
Produced Water Evaporator
Sichuan Petroleum Administration

Facility |
Sichuan Petroleum Administration |
Location |
Chengdu, Sichuan Province, PRC |
Purpose |
Comply with Government regulations to reduce
pollution caused by the discharge of produced water generated
during gas production. |
Project Duration |
Engineering and shipment
Installation
Commissioning
|
7 months
2 Months
3 Weeks
|
Technical Data |
Water Evaporation Rate
Feed Flow Rate
Feed Concentration
Final Concentration
Configuration
Cost |
2700 Barrels/Day
3000 Barrels/Day
8%
24%
Single Effect, Vapor Compression (All Electric)
$0.11/Barrel |
Process Flow

Project Scope
J&Y provided all engineering for a system that met all contractual
requirements for evaporation and concentration and provided all equipment
required for a functional system. This included evaporators, heat
exchangers, blowers, tanks, pumps, valves, instrumentation, PLC control
system, structural steel members and piping to achieve the required
result.
Results
The project was fast track and required engineering and equipment
supply in 7 months. To assist in expediting the installation, partial
shipments were made. After a 3 month installation period, the equipment
was commissioned fully tested in 6 weeks. The system exceeded the
design economy and was immediately accepted and placed in full production.
<Back | Top | Home
|